Well it's not concrete yet, but a few months of settling, a couple of layers of tamped sand and stone and it's close.
It's a bit of a religious debate as to where the plastic should be (below stone or below concrete), but I needed to stop the moisture until the slab is poured, so...
no hand tamping here...
My "Sanford & Son" scrap pile had to be replaced by a leach field. YES, more tree and stump removal...
With the cost of stone delivery going through roof these days, it was actually much cheaper, and easier, to go with a chamber system instead...
The prettiest it'll ever be...
Speed levelers ensure that all 3 trenches are used equally...
150 feet of trenches
I just need to back-fill...